We are delighted to confirm that we have been awarded the Groundworks and Adoptable Infrastructure works
on Persimmon and Charles Church new joint development in Roade, Northamptonshire.

The development consists of 292 new dwellings in total, 125 are of piled and ground beam construction
and the remaining 167 are traditional trench fill foundations.

The Infrastructure consists of 11,700 m2 of adoptable roads and 5,165 m of adoptable sewers.  This development is due to commence in November 2015 and be completed by 2019.